Plan every fixing as a hole through the waterproofing layer. That means choosing a position that lands on solid material, away from the wettest part of the wall and off the joints, drilling without cracking the tile, and sealing the fixing once the door has been adjusted rather than before.
The reason is that a fixing is the only part of the installation that deliberately opens the layer water is kept out by. Handled in the right order, the opening is small, it lands on something solid, and it is closed again. Handled in the wrong order, it becomes a slow path into the wall that shows up months later as a damp patch on the other side.
Waterproofing fails at edges and penetrations rather than across the middle of a wall, and each fixing is a penetration. Four places on a shower wall carry more risk than the rest.
Decision rule: if a fixing cannot be placed away from the base, off a joint and onto solid material, move the door's fixing position rather than the fixing method. Moving a hinge plate along the opening is cheaper than repairing a wall.
Drilling into a tiled wall is a five-step job, and the steps exist because each one prevents a specific failure.
Drilling through a joint or directly beside one is the most common way a tile cracks, so the position is chosen in the middle of a tile wherever the door's fixing centres allow it. Where they do not, the fixing position moves rather than the tile being drilled at its weakest point.
A fixing that is not sealed is a hole with a screw in it. The sequence matters more than the product: fix first, adjust the door, then seal around the fixing, then re-check the seal once the door has settled into use.
The order also protects the door: a fixing sealed before the door is set leaves no room to correct the geometry, and correcting it afterwards means cutting the sealant out and starting again.
Five habits cause most of the damage that follows a fixing, and each one is avoidable without extra work.
Where the enclosure makes drilling avoidable altogether, that option is worth taking: the guide to installing without drilling tile covers the arrangements that use existing surfaces instead, and the wall types guide covers what each substrate will accept.
Before drilling, confirm: the material behind each fixing; a position that avoids the base, the joints and the corners; a marking method that will not let the bit skate; a slow start through the glaze; and sealing that happens after the door is adjusted rather than before. Where a fixing lands somewhere uncertain, requirements can vary by jurisdiction - verify applicable local requirements and the product installation instructions before proceeding. The tile installation planning guide covers how the fixing positions are decided in the first place, and the shower doors collection shows the fixings each door is supplied with.